This articleneeds additional citations forverification.(December 2008) |
Themedium tank T20,medium tank T22andmedium tank T23were prototypemedium tanks,developed by theUnited States ArmyduringWorld War II.They were designed as successors to theM4 Sherman.The standard main weapon for production versions of these designs was to be the76 mm gun M1.
Medium tank T20 | |
---|---|
Type | Medium tank |
Production history | |
No.built | T20 - 2 pilot T22 - 2 pilot T23 - 248[1] |
Specifications | |
Mass | 29.83 t (29.36 long tons; 32.88 short tons) |
Length | 5.70 m (18 ft 8 in) |
Width | 3.00 m (9 ft 10 in) |
Height | 2.44 m (8 ft 0 in) |
Crew | 5 (Commander, gunner, loader, driver, co-driver) |
Armor | 62 mm |
Main armament | 76 mm gun M1A1 70 rounds |
Secondary armament | 2x.30 calBrowning M1919machine guns 6,000 rounds |
Engine | GAN V-8 petrol |
Power/weight | 17.26/ton |
Suspension | HVSS (Horizontal Volute Spring Suspension) |
Operational range | 160 km (99 mi) |
Maximum speed | 40 km/h (25 mph) |
In July 1943, on the basis that the 75 mm-armed M4 was becoming obsolete, theUS Army Ordnance Departmentrequested that the 76 mm-gunned T23E3 and T20E3 go into production as theM27andM27B1.However, the request was rejected and neither design was ever mass-produced. The Army did not consider it necessary to interrupt M4 production for a vehicle for which they did not perceive a requirement and the introduction of the 76 mm gun to the tank force was opposed by the Armored Ground Force.
Successive evolution of the basic design culminated in theM26 Pershing.
Design and development
editAlmost immediately after the M4 Sherman was standardized, the US Ordnance Department started work on a successor. The Ordnance Department had already been working on a heavily armoredinfantry tankdesign for the British, using M4 parts.[2]The new project was started on the 25 May 1942, it was originally designatedM4X.[3]The specification was 32 short tons, "automatic" 75mm gun, 4 in (100 mm) of armor and a top speed of 25 mph (40 km/h).[4]
After a wooden mockup produced byFisher,Ordnance (in agreement with Armored Force Board) set out three pilot models to be built with different combinations of armament but interchangeable turrets. All would use theFord GAN V-8engine driving Hydra-matic transmission through atorque converter.The T20 would have the 76mm gun, the T20E1 the automatic 75mm and the T20E2 a 3-inch gun. T20 and T20E1 would be fitted withhorizontal volute spring suspension(HVSS) but the T20E2 would have hadtorsion barsuspension.[4]
Starting with the T20, the Ordnance Department initially developed three series of improved medium tank prototypes, the T20, T22, and T23. The main differences between the T20, T22 and T23 lay in the choice of transmission.[4]The T20 used a torque converter fluid drive, the T22 a 5-speed mechanical drive similar to the M4 drive, and the T23 used an electric drive. All moved the transmission to the rear of the vehicle eliminating the need for a driveshaft running the length of the vehicle. The driveshaft used in the M3 and M4 vehicles forced the turret to be mounted higher increasing the vehicle height.
T20 series
editAll the T20 models used the FordGAN V8engine with Torqmatictorque convertertransmission with rear drive sprocket. The hull was all-welded construction and the turrets cast.[4]
- T20
- 76 mm gun M1and horizontal volute spring suspension. Built by Fisher and completed in June 1943.[4]
- T20E1
- Planned to be 75 mm automatic gun and horizontal volute spring suspension but cancelled and turret used on the T22E1.[4]
- T20E2
- Intended to have 3 inch gun and torsion bar suspension but completed by Fisher with 76mm gun and designated T20E3.[3]
- T20E3
- 76 mm gun and torsion bar suspension[4]
The T20 and T20E3 were tested but the transmission leaked and overheated. Any further work on them was stopped at end of 1944.[4]
T22 series
editWork on T22 started in October 1942 when Chrysler were contracted to build pilot tanks that were identical to the T20 including the Ford GAN V8 except for using the M4 Sherman transmission though rear wheel drive rather than positioned in the front of the Sherman's.[5]Both vehicles were built by June 1943 but as with the T20 there were transmission issues and work on the T22 was cancelled in December 1944.[5]
- T22
- 76 mm gun and horizontal volute spring suspension
- T22E1
- First T22 pilot refitted with the turret built by United Shoe Machinery Corporation for the cancelled T20E1.[5]75 mm automatic gun and horizontal volute spring suspension[6]The gun was a 75mm M3 on mount M34 which was fed by a hydraulic loader from two magazines – one with AP shells and the other with HE.[5]
- T22E3
- Equivalent of the T20 with 3-inch gun; cancelled during design stage.[5]
There was only one T22 constructed. The T22E1 was the T22 pilot vehicle re-equipped with the turret originally built for the T20E1. The 75 mm automatic gun was tested in this installation and gave a maximum rate of fire of 20 rounds a minute, but was abandoned in December 1944 on the basis that it was unreliable and larger calibre guns were now the priority.
T23 series
edit
The T23 design was to be similar to the T22 but using aGeneral Electricsupplied electric transmission with M4 tracks and VVS suspension.
As with T20 and T22, three pilot models were ordered from Detroit Arsenal with different armament T23 with 76mm, T23E1 with automatic 75mm and T23E2 with 3-inch gun.[7]The 75mm and 3-inch designs were cancelled before completion but the first T23 was completed and entered trials before the T20 or T22 designs; the second was ready by March 1943.[7]The T23 was found to be highly maneuverable.
- T23
- 76 mm gun and vertical volute suspension[6]Electric transmission.
- T23E1
- automatic 75mm. Cancelled.
- T23E2
- 3-inch gun. Cancelled
- T23E3
- 76 mm gun andtorsion bar suspension
- T23E4
- 76 mm gun and horizontal volute suspension. Cancelled
The design was classified "limited procurement" in May 1943 and 250 T23s were ordered; these were built between November 1943 and December 1944[7]although the design was never standardized or issued to front line units. Production models featured the T80 gun mount and M1A1 76mm gun. The turret would later be used in modified form for 76mm M4 variants. The T23 was not adopted for service partly because of its untried transmission system and partly because the design had poor weight distribution and excessive ground pressure. In an attempt to rectify this, two further variants were ordered, the T23E3 with torsion bar suspension and the T23E4 with horizontal volute suspension. The T23E4 was cancelled before the design was completed, but the T23E3 prototype was completed and the torsion bar suspension was found to have reduced the ground pressure by 20% compared to the T23. Despite cancellation of the T23E4, three T23 tanks (serial numbers 624, 625, and 626) were converted in 1944 to horizontal volute suspension. Mobility trials demonstrated this configuration to be superior to vertical volute but inferior to torsion bar suspension.[8]
T21 Light Tank
editIn a related development the T21 was proposed as a replacement for theM3 and M5 series light tanks.It was to have been based on the hull and turret design of the T20 but with a maximum armor thickness of 30 mm (1.2 in) it would weigh only 24 short tons (22 t) been armed with the 76 mm gun, used either a torsion bar or use the vertical volute spring suspension of theM7 Medium Tank(originally known as T7 Light Tank).[9]
The design was prepared, but the two planned pilots were built; Armored Force wanted light tanks to weigh no more than 20 short tons (18 t). Ultimately, the T21 concept was superseded by the T24 program, which was standardized as theM24 Chaffee.[9]
Further development
editWith standardization of the M27 rejected, the Ordnance Department continued designing improved tanks, this time armed with 90 mm guns. The immediate result of this line of development was theT25 series– essentially a slightly larger version of the T23 – and then the bigger, better protected T26. The T26 further evolved into the T26E3, and was ultimately standardized as theM26 Pershingand accepted into service in 1944.
See also
editReferences
edit- ^"T23 Средний танк"[T23 Medium Tank].aviarmor.net(in Russian). 2 September 2018.
- ^Steven J. Zaloga, Tony Bryan, Jim LaurierM26/M46 Pershing Tank 1943-53Osprey Publishing p6
- ^ab"Medium Tank T20 Prototype Medium Tank - United States".militaryfactory.Retrieved20 November2019.
- ^abcdefghChamberlain & Ellis 1981,p. 149.
- ^abcdeChamberlain & Ellis 1981,p. 150.
- ^ab"T23 Medium Tank".Tank Encyclopedia.23 September 2016.Retrieved20 November2019.
- ^abcChamberlain & Ellis 1981,p. 151.
- ^"American Electro-tank".Tank Archives.12 April 2021.Retrieved20 December2024.
- ^ab"T21 Light Tank".historyofwar.org.Retrieved20 November2019.
Sources
edit- Chamberlain, Peter; Ellis, Chris (1981) [1969],British And American Tanks of World War II(2nd US ed.), Arco
- TM 9-734 (1944)
- TM 9-1734 (1944)
- SNL G183
External links
edit