Jump to content

HVDC Cross-Channel

From Wikipedia, the free encyclopedia
HVDC Cross-Channel
Interconnexion France Angleterre
Sellindge Converter Station on the UK side of the interconnector
Sellindge Converter Station on the UK side of the interconnector
Map
Location of Cross-Channel
Interconnexion France Angleterre
Location
CountryFrance,United Kingdom
General directionNorth-South
FromSellindge,United Kingdom
Passes throughEnglish Channel
ToBonningues-lès-Calais,France
Ownership information
PartnersNational Grid plc
Réseau de Transport d'Électricité
Construction information
Manufacturer of conductor/cableAlstom
Manufacturer of substationsASEA(160MW scheme);Alstom(2,000MW scheme)
Construction started1985 (2,000MW scheme)
Commissioned1986 (2,000MW scheme)
Technical information
Typesubmarine cable
Type of currentHVDC
Total length73 km (45 mi)
Power rating2,000MW
AC voltage400kV
DC voltage±270kV
No.of poles4 (2 bipoles)

TheHVDC Cross-Channel(French:Interconnexion France Angleterre IFA 2000) is the 73-kilometre-long (45 mi)high-voltage direct current(HVDC)interconnectorthat has operated since 1986 under theEnglish Channelbetween thecontinental European gridatBonningues-lès-Calaisand the Britishelectricity gridatSellindge.The cable is also known asIFA,[1][2]and should not be confused with the newIFA-2,another interconnect with France that is three times as long but only half as powerful.

The current 2,000MW link is bi-directional and the countries can import or export depending upon market demands, mostly depending upon weather conditions and availability of renewable energy on the British Isles, and French surplus of nuclear generation or demand for electric heating. It was completed in 1986, and replaced the first cross-Channel link which was a 160MW link completed in 1961 and decommissioned in 1984.

A fire in September 2021 caused the link to be removed from service. National Grid announced that half of its capacity would be restored on 20 October 2021, with full capacity being restored by October 2023.[3]

160 MW system (1961)

[edit]

The first HVDC Cross-Channel scheme was built byASEAand went into service in 1961,[4]betweenconverter stationsatLyddin England (next toDungeness Nuclear Power Station) andEchinghen,nearBoulogne-sur-Mer,in France. This scheme was equipped withmercury-arc valves,each having fouranodesin parallel.[5]

In order to keep the disturbances of themagnetic compassesof passing ships as small as possible, abipolar cablewas used. The cable had a length of 65 km (40 miles) and was operated symmetrically at a voltage of ±100kV and a maximum current of 800amperes. The maximum transmission power of this cable was 160megawatts (MW). The cable was built byABB.[6]Given that the cable was laid on the surface of the seabed it was prone to being fouled by fishing nets, causing damage. Whilst repairs were undertaken there was considerable down time on the circuit resulting in a loss of trading. Indeed, by 1984 the circuit was disconnected from the Main Transmission System.

2,000 MW system (1986)

[edit]

Because the first installation did not meet increasing requirements, it was replaced in 1975–1986 by a new HVDC system with a maximum transmission rating of 2,000MW between France and the United Kingdom, for which two new converter stations were built inSellindge,betweenAshfordandFolkestoneinKent,England and inBonningues-lès-Calais(Les Mandarins station), nearCalais,France. Unlike most HVDC schemes, where the two converter stations are built by the same manufacturer, the two converter stations of the 2,000MW scheme were built by different manufacturers (although both have subsequently become part of the same parent company,Alstom). The Sellindge converter station was built byGEC[7]and the Les Mandarins converter station was built by CGE Alstom.

This HVDC-link is 73 km (45 miles) long in route, with 70 km (43 miles) between the two ends. The undersea section consists of eight 46 km (29 miles) long 270kVsubmarine cables,laid between Folkestone (UK) andSangatte(France), arranged as two fully independent 1,000MW Bipoles, each operated at a DC voltage of ±270kV. Cables are laid in pairs in four trenches so that the magnetic fields generated by the two conductors are largely cancelled. The landside parts of the link consist of 8cables with lengths of 18.5 km (11.5 miles) in England, and 6.35 km (3.95 miles) in France.[8]

In common with the 1961 scheme, there is no provision to permit neutral current to flow through the sea. Although each station includes an earth electrode, this is used only to provide a neutral reference, and only one of the two electrodes is connected at a given time so that there can be no current flow between them.

The system was built with solid-state semiconductorthyristor valvesfrom the outset. Initially these were air-cooled and used analogue control systems, and in 2011 and 2012 respectively, the thyristor valves of Bipole 1 and Bipole 2 were replaced by modern water-cooled thyristor valves and digital control systems supplied by Alstom.[9]

This system remains the world's largest-capacity submarine cable HVDC system.[10]

In November 2016, duringStorm Angus,a ship dragging an anchor cut four of the eight cable components, reducing capacity by 50%.[11]Repairs were completed by the end of February 2017. The equipment occasionally faults, causing capacity to drop: in a bad year, this might happen several times. To maintain grid frequency and power, the National Grid has a variety offrequency responseassets, of whichmarket batteriesare the first to respond.[12]

In September 2021, a major fire at the Sellindge converter station led to the shutdown of the link.[13][14]National Grid initially announced that half of the link capacity would be restored within a fortnight, with full capacity being restored in March 2022. The shutdown came at a time of high prices and supply shortage in the UK electricity market, caused by low wind speeds and high prices for natural gas.[15][16]On 15 October 2021, National Grid announced that half of the link capacity would be restored within the next few days, that 75% capacity would be available between October 2022 and May 2023, and that they hoped to restore full capacity by October 2023.[3]

Significance

[edit]

Since the commissioning of the 2,000MW DC link in the 1980s, the bulk of power flow through the link has been from France to Britain. However, France imports energy as needed during the winter to meet demand, or when there is low availability of hydroelectric power.

As of 2005,imports of electricity from France have historically accounted for about 5% of electricity available in the UK. Imports through the interconnector have generally been around the highest possible level, given the capacity of the link. In 2006, 97.5% of the energy transfers were made from France to UK, supplying the equivalent of 3million English homes. Prior to the 2021 fire, the link availability was around 98%, which was among the best rates in the world. The continued size and duration of the flows are open to some doubt, given the growth in demand in continental Europe for clean electricity, and increasing electricity demand within France.[17]

Sites

[edit]
Site Coordinates
Echingen converter station 50°41′48″N1°38′21″E/ 50.69667°N 1.63917°E/50.69667; 1.63917(Cross-Channel ( old) – Echingen Converter Station)
Lydd converter station 50°54′54″N0°56′50″E/ 50.91500°N 0.94722°E/50.91500; 0.94722(Cross-Channel ( old) – Lydd Converter Station)
Les Mandarins converter station 50°54′11″N1°47′5″E/ 50.90306°N 1.78472°E/50.90306; 1.78472(Cross-Channel ( new) – Les Mandarins Converter Station)
Sellindgeconverter station 51°6′21″N0°58′32″E/ 51.10583°N 0.97556°E/51.10583; 0.97556(Cross-Channel ( new) – Sellindge Converter Station)

See also

[edit]

References

[edit]
  1. ^"IFA".
  2. ^"Interconnector customer portal | National Grid Group".
  3. ^abAmbrose, Jillian (15 October 2021)."Kent's burnt-out electricity cable will take two more years to get back to full service".The Guardian.Retrieved15 October2021.
  4. ^Compendium of HVDC schemes,CIGRÉ,Compendium of all HVDC projects.Archived2014-07-28 at theWayback Machine
  5. ^Cory, B.J., Adamson, C., Ainsworth, J.D., Freris, L.L., Funke, B., Harris, L.A., Sykes, J.H.M., High-voltage direct current converters and systems, Macdonald & Co. (publishers) Ltd, 1965, p175–218.
  6. ^"60 years of HVDC"(PDF).ABB Group.Retrieved6 March2018.
  7. ^Rowe, B.A., Goodrich, F.G., Herbert, I.R., Commissioning the Cross Channel h.v.d.c. link,GECReview, Vol. 3, No. 2, 1987.
  8. ^Compendium of HVDC schemes,CIGRÉTechnical Brochure No. 003, 1987, pp194–199.
  9. ^"Anglo – French HVDC Link"(PDF).Areva.2009-12-01. Archived fromthe original(PDF)on July 8, 2014.Retrieved2010-02-28.
  10. ^"HVDC Submarine Power Cables in the World"(PDF).Joint Research Centre.Retrieved6 March2018.
  11. ^"How a Loose Anchor Cut Up Britain's Power Link With France".Bloomberg News.2 December 2016.
  12. ^Stoker, Liam (5 June 2019)."Batteries act as first responders when UK-France interconnector trips".Energy Storage News.
  13. ^"National Grid site fire shuts down power cable between France and UK".BBC News.15 September 2021.
  14. ^Ambrose, Jillian (15 September 2021)."Fire shuts one of UK's most important power cables in midst of supply crunch".The Guardian.London.
  15. ^"Fire-damaged power link will be out for six months, says National Grid".Sky News.16 September 2021.
  16. ^"The UK's Energy Price Surge Could be Just Getting Started".Pound Sterling Live.16 September 2021.
  17. ^"UK Government Web Archive".
[edit]