Iran–Pakistan gas pipeline

From Wikipedia, the free encyclopedia

Iran–Pakistan gas pipeline
Location
CountryIran
Pakistan
General directionIran to Pakistan:WestEast
Within Pakistan:SouthNorth
FromAsalouyeh,Bushehr,Iran
Passes throughBandar-Abbas
Iranshahr
Khuzdar
Sui
ToMultan,Punjab,Pakistan
General information
TypeNatural gas
PartnersNational Iranian Oil Co.
Sui Northern Gas Pipelines
Sui Southern Gas Pipelines.
Gazprom JSC
ExpectedDecember 2017[1]
Technical information
Length2,775 km (1,724 mi)
Maximum discharge40 billion cubic metres (1.4×10^12cu ft) per year
Diameter56 in (1,422 mm)

TheIran–Pakistan gas pipeline,also known as thePeace pipeline,orIP Gas,[2]is an under-construction 2,775-kilometre (1,724 mi)pipelineto delivernatural gasfromIrantoPakistan.

Although construction of the pipeline began in 2011, the Pakistani government did not officially approve its work until 2024.[3][4]

History

[edit]

Inception

[edit]

The idea was conceived by a young Pakistani civil engineer Malik Aftab Ahmed Khan (Sitara e Jurat), a graduate of NED University, in mid-1950, when an article of his was published by the Military College of Engineering, Risalpur, Pakistan. The articlePersian Pipelinealso mentioned the method for its protection along the hostile territory by establishing mini battalion-size cantonments along its proposed route through Balochistan/Sindh.[5][6]The project was conceptualized in 1989 byRajendra K. Pachauriin partnership with Ali Shams Ardekani and Sarwar Shar, former Deputy Foreign Minister of Iran. Pachauri proposed the plan to both Iranian and Indian governments. The government of Iran responded positively to the proposal. At the 2010 annual conference of theInternational Association of Energy Economics,Ardekani backed Pachauri's proposal.[6]

Timeline

[edit]

Discussions between the governments of Iran and Pakistan started in 1995.[7]A preliminary agreement was signed in 1995. This agreement foresaw construction of a pipeline fromSouth Pars gas fieldtoKarachiin Pakistan. Later Iran made a proposal to extend the pipeline from Pakistan into India. In February 1999, a preliminary agreement between Iran and India was signed.[8]

In 2004 the project was revived after theUNDP's reportPeace and Prosperity Gas Pipelinesby Pakistanipetroleum engineer,Gulfaraz Ahmed, was published in December 2003. The report highlighted benefits of the pipeline to Pakistan, India and Iran.[9]

In February 2007, India and Pakistan agreed to pay Iran US$4.93 per million British thermal units (US$4.67/GJ) but some details relating to price adjustment remained open to further negotiation.[10]

In April 2008, Iran expressed interest in the People's Republic of China's participation in the project.[11]In August 2010, Iran invitedBangladeshto join the project.[12]

In 2009, India withdrew from the project over pricing and security issues, and after signing a civilian nuclear deal with the United States in 2008.[13][14]However, in March 2010 India called on Pakistan and Iran for trilateral talks to be held in May 2010 inTehran.[15]

On 4 September 2012, the project was announced to commence before October 2012 and be completed by December 2014.[16]

On 30 January 2013, the Pakistan's federal government approved a deal with Iran for laying the Pakistan's segment of a pipeline.[17]On 27 February 2013, the construction of the Pakistani section was agreed.[18][19]On 11 March 2013, the construction work on the Pakistani section of the pipeline was inaugurated bypresident of PakistanAsif Ali Zardariandpresident of IranMahmoud Ahmadinejad.[20][21][22]According with Javad Owji, managing director of theNational Iranian Gas Company,the pipeline in Pakistan is expected to be constructed in 22 months with the participation of Iran.[23]

On 27 May 2013, Iranian deputy minister for petroleum, A. Khaledi, in a letter to thePakistangovernment expressed concern over the delay in the start of the Pakistani portion of the pipeline. He said that after a government-to-government agreement between the two countries, they were supposed to select entities for the construction of the latter part of the pipeline. Pakistan still hasn't officially nominated Tadbir Energy and local sub-contractors to begin work on the Pakistani half of the pipeline.[24]

On 12 June 2013, the newly elected prime minister ofPakistan,Nawaz Sharif,allayed any fears regarding the abandonment of the project and said that the Pakistani government is committed to the fulfillment of the project and targets the first flow of gas from the pipeline in December 2014. The premier also stated that his government is planning to commit to theTurkmenistan-Afghanistan-Pakistan-India gas pipelineproject as well.[1]

On 28 November 2013, a 'friendly' country anonymously offers $1 billion to help fund the pipeline.[tribune.com.pk 1]

On 10-November-2013, a meeting betweenPakistanFederal Minister for Petroleum and Natural ResourcesShahid Khaqan Abbasiand Iranian Minister of PetroleumBijan Namdar Zangenehheld at the Ministry of Petroleum atTehran.The Pakistani Officials assured their Iranian counterparts that project would continue despite "external pressure".[25]

On 25-Feb-2014, Minister for Petroleum and Natural Resources Pakistan, Shahid Khaqan Abbasi told theNational Assemblythat the project for the moment is off the table, he citedinternational sanctionsas the issue, he said "In the absence of international sanctions the project can be completed within three years, but the government cannot take it any further at the moment because international sanctions against Iran are a serious issue". Pakistan will face the penalty if it failed to lay its side of pipeline till December 2014. Analysts however points atSaudi Arabia's pressure to not to carry out the project.[26]

Iran plans to abandon this pipeline project, as per April 2014 news article.[27]

During the state visit ofPrime Minister Nawaz ShariftoIranin May 2014, both the government stated to remain committed on the completion of the pipeline and also agreed to extend the completion date by one year.[28]However, on 30 May 2014,ISNA news agencyquoted Iranian Deputy Oil Minister for International and Trade Affairs Ali Majedi as claiming that the deadline has not been extended as no such agreement was signed during Nawaz Sharif's visit and the deadline to complete is still December, 2014.[29]

During the year 2017, India is planning to disassociate from this pipeline project and working on cheaper independent under sea pipe line directly from Iran.[30]

As of early 2019, the project remains substantially delayed. While the Iranian section of the pipeline has been completed, the Pakistani section remains under construction and subject to renewed delays thanks to concerns about the US sanctions regime.[31][32]

On 23 February 2024, Pakistan approves construction of Iran-Pakistan gas pipeline amid fear of a potential 18 billion US dollar penalty for failing to complete the project on time.[33]

Controversies

[edit]

In January 2010, the United States asked Pakistan to abandon the pipeline project. If canceling the project, Pakistan would receive assistance from the United States for construction of a liquefied natural gas terminal and importing electricity fromTajikistanthroughAfghanistan'sWakhan Corridor.[34]However, on 16 March 2010 inAnkara,Iran and Pakistan signed an agreement on the pipeline.[13]According to the agreement each country must complete its section by 2014.[35]In July 2011, Iran announced that it has completed construction of its section.[36]If Pakistan does not fulfill its obligation to complete the pipeline on its side by the end of 2014, it will have to pay a daily penalty of $1 million to Iran until completion.[37]On 13 March 2012 Pakistan's ministry of finance announced that private investors were showing diminished interest and that the government might have to impose a tax on consumers, or seek government-to-government arrangements with Iran, China and Russia to build the pipeline. On 29 March it was reported that officials from Pakistan's petroleum ministry would travel to Russia in early April for talks withGazprom.[35]Then, in a 7 April article the Pakistani dailyPakTribunereported that Gazprom would both finance and construct the pipeline. This would require setting aside the Public Procurement Regulatory Authority rules which require international bidding for such a large project. TheEconomic Coordination Committeewould be asked in its next meeting to give such permission. The article also informed that the reason the private consortium no longer would contribute to the project was US opposition.[37]

On 15 April 2012, it was reported through unnamed diplomatic sources inIslamabadthatSaudi Arabiawas offering to deliver an "alternative package" to Pakistan if the country abandoned its cooperation with Iran. In addition to oil the package would also include a cash loan and oil facility. The news came in connection with a visit to Pakistan by the Saudi deputy foreign minister.[38]

On 1 May 2012, it was reported that Pakistan's foreign minister,Hina Rabbani Kharhad said that Islamabad will not give in to US pressures to mothball the project and will finish the huge pipeline project "at any cost" and that the project was in line with the country's national interest.[39]

On 29 January 2013, US consul generalMichael Dodmanthreatened Pakistan with economical sanctions if it does not abandon the project.[40]

In late October 2013, Sustainable Policy Development Institute published a report in which the proposed pipeline was termed as "death sentence" for Pakistan. Since the prices in the contract are linked to crude oil prices, the government "blatantly ignored the energy dynamics and its pricing while going for this deal". The gas sold to Pakistan will be higher priced than the current domestic prices of gas in the country.[41]

Route

[edit]

The length of the pipeline that will be supplied from the South Pars field has been given variously as 900 kilometres (560 mi),[13]1,035 kilometres (643 mi),[14]and 2,775 kilometres (1,724 mi).[42]It starts fromAsalouyehand stretches 1,172 kilometres (728 mi) through Iran. The Iranian section is known as Iran's seventh cross-country gas pipeline. The first 902-kilometre (560 mi) part of this section runs from Asalouyeh toIranshahr.The second 270-kilometre (170 mi) part runs from Iranshahr to the Iran–Pakistan border.[43]

In Pakistan, the length of the pipeline is 785 kilometres (488 mi).[17]It will pass throughBaluchistanandSindh.[13]InKhuzdar,a branch would spur off to Karachi, while the main pipeline will continue towardsMultan.From Multan, the pipeline may be expanded toDelhi.[44]The route in Pakistan may be changed if China will participate in the project.[45]

As there are concerns over the pipeline being attacked byBaluchi insurgents,an alternative offshore route from Iran to themaritime boundarybetween India and Pakistan offKutchwas proposed. According to this proposal, from there one branch was to run to Pakistan while other branch to run to Kutch.[46][47]

Technical description

[edit]

The initial capacity of the pipeline was to be 22 billion cubic metres (780 billion cubic feet) of natural gas per year, which was expected to be raised later to 55 billion cubic metres (1.9 trillion cubic feet).[48]However, as a bilateral project between Iran and Pakistan, the pipeline will carry only 8.7 billion cubic metres (310 billion cubic feet) of gas per year as contracted and 40 billion cubic metres (1.4 trillion cubic feet) as a maximum capacity. The pipeline has a diameter of 56 inches (1,400 mm).[49]It is expected to cost US$7.5 billion and to be commissioned by 2013.[7][49]

It is expected that gas delivered from Iran through the pipeline will cost US$11 permillion British thermal units($38/MWh) compared to $13 per million British thermal units ($44/MWh) which is expected to be price of gas delivered through the proposedTrans-Afghanistan Pipelineand $18 per million British thermal units ($61/MWh) of importedLNG.[50]

Authorities blamed Lack of safety measures and old infrastructure for the Thursday 14 March 2019 explosion in a gas pipeline near the city ofMahshahrin southern Iran. One child, one woman and two others were killed in the explosion.[51]

Companies

[edit]

In different times several companies have been interested to build the pipeline. Companies includedGazprom,BHP,National Iranian Gas Company,Petronas,andTotal.A consortium consisting ofRoyal Dutch Shell,BG Group,Petronas and an Iranian business group had negotiated on exporting of gas from South Pars to Pakistan. From India,GAILhad been involved.[44]However, the pipeline's section in Iran was built by theNational Iranian Gas Company.It usedKhatam al-Anbiaas a subcontractor.[43]In Pakistan,Inter State Gas Systemsis responsible for the construction of the pipeline. [52]The contract for engineering, procurement, construction and financing of the Pakistan's section was signed with Iran's Tadbir Energy. Iran agreed to provide a $500 million loan for construction payable in 20 years.[17]However, on 13-December-2013, Pakistan's Minister for Petroleum and Natural Resources Shahid Khaqan Abbasi said that Iran refused to fund the project citing 'acute financial constraint' as the reason. Pakistan authorities however said to remain committed with the project. Both sides have decided to constitute a working group which would re-establish in two months the new parameters for the projects, including a new time-frame and other important issues involving financing of pipeline to be laid down in the territory of Pakistan.[53][54]

See also

[edit]

References

[edit]
  1. ^abBhutta, Zafar (13 June 2013)."Annual plan 2013–14: Govt will not scrap Iran gas pipeline project".The Express Tribune.Retrieved1 July2013.
  2. ^"The 'peace pipeline'".The National.28 May 2009.Retrieved17 April2013.
  3. ^Islamuddin, Sajid."Pakistan approves work on long-awaited Iran-Pakistan gas pipeline project".Anadolu Ajansı.Retrieved23 February2024.
  4. ^"Pakistan Begins Work on Iran-Pakistan Gas Pipeline Segment Despite US Sanctions".Pipeline Technology Journal.Retrieved14 March2024.
  5. ^ Shahid, Kunwar khuldune (25 November 2011)."Iran-Pakistan gas pipeline traversing history".Pakistan Today.Retrieved26 November2011.
  6. ^abul Haq, Noor (31 July 2010)."Iran-Pakistan Peace Pipeline. IPRI Factfile"(PDF).Islamabad Policy Research Institute. Archived fromthe original(PDF)on 11 June 2014.Retrieved20 November2011.
  7. ^ab "IPI Implementation Nearing 'Final Stage' – Pakistani Official".Downstream Today.Xinhua News Agency.8 May 2008.Retrieved10 May2008.
  8. ^ Chaudhary, Shamila N."Iran to India Natural Gas Pipeline: Implications for Conflict Resolution & Regionalism in India, Iran, and Pakistan".School of International Service.Retrieved20 March2010.
  9. ^"'Iran-Pakistan gas pipeline project is a lifeline for Pakistan's economy,' Dr Gulfaraz Ahmed, Energy Expert ".Business Recorder.Archived fromthe originalon 18 July 2013.Retrieved1 July2013.
  10. ^ "Peace Pipeline Contract Soon, Gas Flow by 2011".Iran Daily.1 July 2007. Archived fromthe originalon 6 May 2008.Retrieved10 May2008.
  11. ^ "Ahmadinehjad Would Welcome Chinese Role in Gas Pipeline".Downstream Today.Xinhua News Agency.28 April 2008.Retrieved10 May2008.
  12. ^ Kabir, Humayan (15 August 2010)."Iran invites Bangladesh to join cross-border gas grid".The Financial Express.Retrieved20 November2011.
  13. ^abcd Haider, Zeeshan (17 March 2010)."Pakistan, Iran sign deal on natural gas pipeline".Reuters.Archived fromthe originalon 4 January 2013.Retrieved20 March2010.
  14. ^ab "Pakistan gas pipeline is Iran's lifeline".UPI.19 March 2010.Retrieved20 March2010.
  15. ^ "New Delhi calls for IPI talks".UPI.19 March 2010.Retrieved20 March2010.
  16. ^"Iranian gas will start flowing from December 2014: Dr Asim Hussain".The Express Tribune.4 September 2012.Retrieved4 September2012.
  17. ^abc"Pakistan Ratifies Iran-Pakistan Pipeline Agreement".31 January 2013. Archived fromthe originalon 2 April 2016.Retrieved2 February2013.
  18. ^"Pakistan Ratifies Iran-Pakistan Pipeline Agreement".27 February 2013. Archived fromthe originalon 2 April 2016.Retrieved28 February2013.
  19. ^"Pakistan, Iran agree to complete gas pipeline in 15 months".28 February 2013.Retrieved28 February2013.
  20. ^ "Pakistan-Iran gas pipeline defies US".BBC News.11 March 2013.Retrieved11 March2013.
  21. ^ "Zardari, Ahmedinijad inaugurate Pak-Iran gas pipeline project".The Nation.11 March 2013.Retrieved11 March2013.
  22. ^"Pakistan-Iran gas pipeline inaugurated defying US opposition".Euronews.11 March 2013. Archived fromthe originalon 26 September 2020.Retrieved11 March2013.
  23. ^"Iran to complete gas line to Pakistan in 22 months: Official".27 February 2013. Archived fromthe originalon 21 May 2013.Retrieved28 February2013.
  24. ^Bhutta, Zafar (10 June 2013)."Iran upset about slow progress on gas pipeline".The Express Tribune.Retrieved1 July2013.
  25. ^Agencies (10 December 2013)."Pakistan to push forward gas project with Iran".Retrieved18 May2016.
  26. ^The Newspaper's Staff Reporter (25 February 2014)."Iran gas project off the table: minister".Retrieved18 May2016.
  27. ^"Farsnews".Archived fromthe originalon 8 May 2015.Retrieved18 May2016.
  28. ^AFP – APP (12 May 2014)."Pakistan, Iran to go ahead with gas project".Retrieved18 May2016.
  29. ^"Iran denies claims regarding completion date of Iran-Pakistan gas pipeline".The Nation.31 May 2014.Retrieved18 May2016.
  30. ^"Undersea pipeline from Iran can bring cheaper gas to India: TNR Rao".Retrieved7 September2017.
  31. ^Hasnain, Khalid (2 January 2019)."IP gas project in limbo: Pakistan wants Iran to interpret sanctions".Dawn.Pakistan.Retrieved11 May2019.
  32. ^Times, EurAsian (8 May 2019)."Islamabad Keen To CompleteSuper-Delayed' Iran-Pakistan Gas Pipeline ".EurAsian Times: Latest Asian, Middle-East, EurAsian, Indian News.Retrieved11 May2019.
  33. ^"Pakistan approves construction of Iran-Pakistan gas pipeline amid fear of penalty".The Times of India.24 February 2024.ISSN0971-8257.Retrieved25 February2024.
  34. ^"US asks Pak to pull out of Iran gas pipeline project to qualify for extensive assistance".Thaindian News.ANI.14 January 2010. Archived fromthe originalon 4 March 2016.Retrieved20 March2010.
  35. ^ab Anwar, Haris (29 March 2012)."Pakistan Seeks Russia's Help to Finance Iran Gas Pipeline".Bloomberg News.Retrieved16 April2012.
  36. ^ Javaid, Zeeshan (14 November 2011)."Pakistan to renegotiate price formula with Iran".Daily Times.Retrieved20 November2011.
  37. ^ab"Russia to help Pakistan build IP gas pipeline".PakTribune.7 April 2012. Archived fromthe originalon 16 October 2017.Retrieved16 April2012.
  38. ^ "Iran gas pipeline: Saudi offer".Dawn.Pakistan. 15 April 2012.Retrieved16 April2012.
  39. ^"Pakistan will not give in to U.S. pressure on Iran pipeline: Khar".Tehran Times.1 May 2012.Retrieved25 February2024.
  40. ^"US warns Pakistan of sanctions over Iran gas pipeline deal".29 January 2013.Retrieved29 January2013.
  41. ^http://sdpi.org/publications/files/IP-Report.pdf[bare URL PDF]
  42. ^"India has quit Iran gas pipeline deal".Agence India Press.6 September 2009. Archived fromthe originalon 5 March 2016.Retrieved2 May2012.
  43. ^ab"Khatam-ol-Anbia to build 2nd phase of IPI gas pipe".Mehr News Agency.10 August 2010. Archived fromthe originalon 20 November 2011.Retrieved20 November2011.
  44. ^ab Shahid, Sohaib (15 January 2007)."Iran-Pak-India gas pipeline: implications and prospects".Business & Finance Review.Jang Group of Newspapers.Archived fromthe originalon 10 April 2010.Retrieved20 March2010.
  45. ^ "Pakistan determined to launch IP Pipeline".Iran Daily.Zawya. 17 November 2011.(subscription required).Retrieved20 November2011.
  46. ^ Swaminathan S. Anklesaria Aiyar (28 December 2008)."IPI gas pipeline, RIP".The Times of India.Retrieved20 March2010.
  47. ^ Syed Fazl-e-Haider (20 November 2011)."Murky politics of gas".Dawn.Pakistan.Retrieved20 November2011.
  48. ^ Bappa Majumdar, Nidhi Verma (29 April 2008)."Iranian president tries to seal India pipeline".Reuters.Archived fromthe originalon 1 February 2013.Retrieved10 May2008.
  49. ^ab"Iran: No security snag in pipeline deal".Tehran Times.7 November 2011. Archived fromthe originalon 15 May 2013.Retrieved20 November2011.
  50. ^ Abdul Rasheed Azad (5 April 2012)."IP pipeline project: Pakistan to pay $6/MM[million]BTU more for gas price".Business Recorder.Retrieved20 March2013.
  51. ^At Least Five Killed In Iran Gas Explosion
  52. ^Javaid, Zeeshan (17 March 2010)."IP pipeline project to cost $3-4bn".Daily Times.Retrieved20 March2010.
  53. ^"Iran withdraws $500 mil funding offer to Pakistan for gas pipeline project".Retrieved18 May2016.
  54. ^"In limbo: Iran takes back pipeline financing deal".12 December 2013.
[edit]