Pelješac Bridge

From Wikipedia, the free encyclopedia

Pelješac Bridge

Pelješki most
Coordinates42°55′58″N17°32′13″E/ 42.9328°N 17.5369°E/42.9328; 17.5369
Carries2-lane wideD8expressway
CrossesNeretva Channel /Bay of Mali Ston
LocaleDubrovnik-Neretva County,Croatia
Characteristics
DesignCable-stayed bridge
Total length2,404 metres (7,887 ft)
Width23.6 metres (77 ft)
Height98 metres (322 ft)
Longest span5 x 285 metres (935 ft)
Clearance below55 metres (180 ft)
Design life100 years
History
DesignerMarjan Pipenbaher
Constructed byChina Road and Bridge Corporation
Construction start30 July 2018
Construction end26 July 2022
Construction cost420.3 million
Opened26 July 2022;2 years ago(26 July 2022)[1][2]
Statistics
TollNone
Location
Map

ThePelješac Bridge(Croatian:Pelješki most,pronounced[pěʎeʃkiːmôːst]) is acable-stayed bridgeinDubrovnik-Neretva County,Croatia.The bridge provides a fixed link from the southeastern Croatiansemi-exclaveto the rest of the country while bypassingBosnia and Herzegovina's short coastal strip atNeum.The bridge spans the sea channel betweenKomarnaon the northern mainland and the peninsula ofPelješac,thereby passing entirely through Croatian territory and avoiding any border crossings with Bosnia and Herzegovina at Neum.

Construction started on 30 July 2018, and the bridge was connected on 28 July 2021.[3][4]The bridge and its access roads opened for traffic on 26 July 2022.[5][6][7][8][9][10]Stonbypass road was opened on 19 April 2023,[11]allowing buses, heavy trucks, and trucks carrying hazardous loads to access the bridge.[12][13][14][15]

Characteristics

[edit]
Installation of the last span segment in July 2021
Deck and cables in July 2021

The original 2007 design for the bridge had a main span of 568 metres (1,864 ft).[16]This design was modified, and the bridge was built as a multi-span cable-stayed bridge with a total length of 2,404 metres (7,887 ft). It comprises thirteenspans,of which seven are cable-stayed; five central 285-metre (935 ft) spans and two outer 203.5-metre (668 ft) spans. Two pylons around the 200-metre (660 ft) x 55-metre (180 ft) navigation channel are 98 metres (322 ft) above sea level and 222 metres (728 ft) above the seabed.[17][18][19]The bridge was designed bySlovenianengineerMarjan Pipenbaher.

Both sides of the bridge are served by access roads, including two tunnels on Pelješac (one 2,467 metres (8,090 ft) and the other 499 metres (1,640 ft) long), as well as two smaller bridges on Pelješac, (one 420 metres (1,400 ft) and another 131 metres (430 ft) long).

History

[edit]
Location of the bridge

Because the Croatian mainland is intersected by a small strip of the coast around the town ofNeumwhich is part of Bosnia and Herzegovina, forming Bosnia and Herzegovina's only outlet to theAdriatic Sea,the physical connection of the southernmost part ofDalmatiawith the rest of Croatia is limited to Croatianterritorial waters.In 1996, Bosnia and Herzegovina and Croatia signed theNeum Agreement,granting Croatia passage through Neum,[20]but the agreement was never ratified. All traffic passing through the Neum corridor has to undergo border checks on goods and persons. Therefore, people travelling from theDubrovnikexclave to mainland Croatia had to pass through two border checks within 9 kilometres (5.6 mi). With Croatia joining theSchengen Areain 2023 (which it was bound to do in accordance with the conditions of itsaccession to the European Union), checks would become considerably more stringent and time-consuming, as theSchengen Borders Coderequires checks not only when entering the Schengen area, but also when exiting it. Thus, someone travelling from Dubrovnik to mainland Croatia through Neum would undergo three distinct border checks: a Croatian (Schengen) exit check, a Bosnian-Herzegovinian entry check and a Croatian (Schengen) entry check.[citation needed]

Construction site in June 2020

The construction of the bridge was publicly proposed in 1997 by Ivan Šprlje, thePrefectof theDubrovnik-Neretva Countyand member of theSocial Democratic Party(SDP).Croatian Democratic Union(HDZ) initially rejected the idea, but in 1998 it gained support of their MPLuka Bebić.In 2000, the bridge was added to the spatial plan of the county and the first construction plans were drawn up.[21]

The construction works on the Pelješac project officially commenced in November 2005 with a grand opening led by then-Prime MinisterIvo Sanader.[21]Despite the price of the bridge project rising significantly compared to the initial estimate, theGovernmentpersisted with the idea of a bridge. The initial design was changed to reflect the concerns of Bosnia and Herzegovina to the first plans. The two sides agreed on the construction of the bridge in early December 2006.[22]

In May 2007, theCroatian Minister of InfrastructureBožidar Kalmetasaid that preparations for the construction of the bridge were going according to plan and that an initial tender was under preparation. Kalmeta added that the question of when the construction works would begin depended on whether a constructor would be selected in the first round.[23]On 11 June 2007,Hrvatske cesteannounced apublic tenderfor the construction of the bridge. On 28 August 2007, the list of bidders was released:Konstruktor,ViaduktandHidroelektra(from Croatia);Dywidag(Germany),Strabag(Austria),Cimolai[it](Italy),Eiffel(France); andAlpine Bau(fromSalzburg,Austria)

Kalmeta confirmed construction works were to start in autumn 2007. The contractor was to be obliged to complete the project in four years. Construction costs were estimated at 1.9 billionHRK,nearly260 million.[24]It would be financed by Hrvatske ceste and by loans by European investment banks.[24]

ASentinel-2image of the bridge.

In June 2007, after the tender was published, the media reported renewed opposition from the State Border Commission in Bosnia and Herzegovina. Bosnia and Herzegovina declared that it would sue Croatia if it started building the bridge unilaterally.[25]

On 14 September 2007, theMinistry of Constructionannounced that the Konstruktor/Viadukt/Hidroelektra consortium had won the contest and that it would sign a contract for 1.94 billionHRK,roughly265 million at the time. Construction works on the northern and southern termini commenced on 24 October 2007,[26]with sea works starting in the autumn of 2008.

In July 2009, theCroatian GovernmentunderJadranka Kosorannounced that, as part of the effort to reduce expenses during the economic crisis, the construction of the Pelješac Bridge was to proceed under a much slower timetable than originally planned. In November 2009, Kalmeta mentioned 2015 as the year of completion. The 2010 budget and road-building programme indicated that by the end of 2012, only 433.5 millionHRKor60 million would be invested in the bridge, which is less than a quarter of the total.[27]

After the2011 Croatian parliamentary election,the newSDP-led governmentterminated the existing construction contract worth 1.94 billionHRK(c.259 million) for lack of funds in May 2012.[28][29][30][31]At the same time, plans were made to use the bridge construction sites as newferrydocking sites.[32][33]There was also discussion regarding how the cost and speed of the ferry solution would compare to that of the cancelled bridge, with theMinister of Maritime Affairs, Transport and Infrastructureclaiming the ferrying would be less expensive and reasonably fast, as well as complete by 1 July 2013, which is when Croatia joined theEuropean Unionand when the new border regime could have become a problem.[34][35]

In 2012, the European Union granted Croatia a sum of200,000 for a pre-feasibility study of the construction of the Pelješac Bridge. The study would examine not only the projected bridge, but also the solution of a closed road corridor across the hinterland of Neum. "The strategic aim of the Government is to effectively connect the territory of Croatia, which is also a goal of the EU, because the Croatian territory is to become a territory of the Union. This project should not be politicized, but rather we should see which action is most cost-effective",Minister of Foreign AffairsVesna Pusićclaimed. She also emphasized that the ratification of theTuđman-Izetbegovićtreaty of 1996 (Neum Agreement) was not a condition to receive European funds for the construction of the bridge, but it would be no harm if it did happen.[36]

The feasibility study prepared by Croatia to analyse the possible alternatives concluded that building a bridge would be the most favourable option as it scored highest in the multi-criteria (safety, impact on traffic, environmental impact) and cost-benefit analysis, compared to the other options; a highway corridor, a ferry connection or the construction of tunnels. The project was prepared in consultation with the authorities of Bosnia and Herzegovina. The necessity to preserve Croatia's natural heritage was an essential criteria taken into consideration at all phases of the project's preparation.[37]

TheEuropean Commissionalso had the project assessed before adoption independent experts in the framework of the Joint Assistance to Support Projects in European Regions (JASPERS)[38]as regards its feasibility and economic viability.[37]

A French study suggested in December 2013 that the bridge is the most feasible solution, andCroatian Minister of TransportSiniša Hajdaš Dončićstated that the construction of the bridge would start in 2015.[39]In July 2015, Croatia's government said that construction was likely to start in spring 2016.[40]

By 2016, the Croatian government was saying construction would go ahead with or without EU funds.[41]Construction dates were further delayed by a formal complaint about tender documents.[42]

Map of the bridge and access roads

The European Commission announced on 7 June 2017 that357 million fromCohesion Policyfunds will be made available for the bridge and the supporting infrastructure (tunnels, bypasses, viaducts and access roads), with completion scheduled for 2022. The EU contribution would amount to 85% of the total construction costs, aiming at benefiting tourism, trade, and territorial cohesion.[37]

Despite protests from Bosnian political actors,Croatian Minister of Regional DevelopmentGabrijela Žalac[43]as well as Croatian Prime MinisterAndrej Plenković[44]confirmed that the construction of the bridge would continue.

On 15 September 2017, it was announced thatChina Road and Bridge Corporation,AustrianStrabagand Italian-Turkish consortiumAstaldi/Içtas applied for a bridge construction tender. The Austrians offered the cost of 2.6 billionHRK(€351 million), the Italian-Turkish offer was 2.6 billionHRK(€341 million), while the Chinese offer was 2.1 billionHRK(€278 million).[45]On 15 January 2018, Hrvatske ceste made a formal decision according to which China Road and Bridge Corporation won the tender. In addition to the lowest price, CRBC also offered to complete the project six months faster than required.[46]Construction had started by mid 2019,[47]with the construction of the bridge pillars in October.[48][49]

Controversial aspects

[edit]

Environmental protection

[edit]

The idea of a large bridge connecting Pelješac to the mainland caused concern among environmental activists in Croatia, who opposed it because of potential damage to sea life in theBay of Mali Ston,as well as tomariculture.[50]These risks and concerns were explicitly addressed by the constructors in preliminary studies.[51]

In October 2015, theCroatian Ministry of Environment and Nature Protectionissued a decision, confirming that a cross-border consultation was carried out concerning the impact of the project on the environment of Bosnia and Herzegovina according to theConvention on Environmental Impact Assessment in a Transboundary Context.Bosnia and Herzegovina did not submit its observations or request an extension of the consultation's timeframe.[citation needed]

Cost-benefit analysis

[edit]

The idea was also opposed for various economic reasons: questions of whether such a bridge was really necessary or whether alternative arrangements could be made with Bosnia and Herzegovina,[52]whether it would be too expensive to build according to environmental standards, and whether it would be better to build anundersea tunnelinstead.[53]

The idea of instead constructing animmersed tubeas a more cost-effective design which did not impede access to Neum was ridiculed and never accepted by the Croatian authorities.[21][54][55]

According to the news programDnevnik Nove TV,another possibility was a highway corridor through Bosnia and Herzegovina with high walls and strict surveillance.[56]

In the process ofaccession of Croatia to the European Union,theCroatian Governmentclaimed that a bridge would be a "prerequisite" for Croatia to enter theSchengen Area.TheEuropean Commissionnevertheless stated in 2010 that this was only one of several options to handle the issue.[57]

International law and access of Bosnia and Herzegovina to the high seas

[edit]

The construction of the bridge was also opposed by various political figures in Bosnia and Herzegovina, mostlyBosniak,who said that it would restrict Bosnia and Herzegovina's access to international waters.[58]Several Bosnian politicians initially opposed the building of the bridge, originally planned to be only 35 metres (115 ft) high, because that would have made it impossible for large ships to enter the harbor atNeum.[59]Although the Neum harbor is not currently suitable for commercial traffic, and most of the trade to and from Bosnia and Herzegovina goes through the Croatian port ofPloče,several Bosnian politicians remarked that a new port might be built in the future, and that the construction of the bridge would frustrate this ambition.

In August 2017, a group of unnamed Bosnian MPs wrote a letter to theHigh Representative of the EU for Foreign Affairs and Security PolicyFederica Mogheriniof Italy, and to theHigh Representative for Bosnia and HerzegovinaValentin Inzkoof Austria, claiming that Croatia was in violation of theUnited Nations Convention on the Law of the Seaand was "cutting off without permission" their country from international waters through the Pelješac Bridge project, calling upon Croatia "to stop attacking the sovereignty of Bosnia and Herzegovina as a maritime state and stop all activities on building an illegal and politically violent bridge project at theKomarna-Pelješaclocation ". The Bosnian MPs noted that Bosnia and Herzegovina had never given formal consent, by theCouncil of Ministersnor by thePresidency,to the bridge project and its financing with EU funds.[60][61]

Croatia stated that the bridge is located exclusively within Croatian territory and Croatian territorial waters and that it is thus entitled under the internationallaw of the seato construct the bridge without requiring any consent from Bosnia and Herzegovina. Croatia also expressed commitment to fully respect the international rights enjoyed by other countries in the Pelješac peninsula, including the right ofinnocent passageenjoyed by all countries under the United Nations Convention on the Law of the Sea, and the right of Bosnia and Herzegovina to have unrestricted access to thehigh seas.Croatia also stated that the expected height of the bridge of 55 metres (180 ft) would allow all current Bosnian shipping to use the existing navigational route to transit under the bridge, and that any ship taller than that which intended to dock at a port in Bosnia and Herzegovina could dock instead at the Croatian port of Ploče, in line with the 1995 Free Transit agreement.

[edit]
Borders of Bosnia Herzegovina (solid line) near Neum as modified (dashed line) according to the 1999 agreement

Bosnia and Herzegovina and Croatia agreed on aborder demarcation treatyin 1998. The treaty was signed by the two former presidents,Alija IzetbegovićandFranjo Tuđman,but it was never ratified by the respective parliaments and so it never entered into force. The agreement included a border between the two countries in the area ofPelješacwhich is slightly different from that shown on maps, since Croatia agreed to recognise the sovereignty of Bosnia and Herzegovina over two small rock islands (Mali ŠkoljandVeliki Školj) and the tip of the peninsula ofKleknearNeum.[43]

On 17 October 2007, thePresidency of Bosnia and Herzegovinaadopted an official position stating that "Bosnia and Herzegovina opposes the construction of the [Pelješac] Bridge until the issues related to the determination of the sea borderline between the two countries are resolved" and asking Croatia not to undertake any unilateral actions concerning the construction of the bridge. Bosnian MPHalid Genjacstated that this official position has never been reversed and is thus still in force, and no official Bosnian body has given its express consent to the construction of the bridge. He argued that "the claims that Croatia is building a bridge on its territory are incorrect because the sea waters beneath the Pelješac Bridge are not and cannot be Croatian or internal waters, but international waters stretching from the territorial waters of Bosnia and Herzegovina to the open sea".[43][62]

TheBosniakmember of the Presidency,Bakir Izetbegović,stated that he believed Croatia should not proceed with the building of the bridge before the maritime border demarcation was agreed, based on the 2007 position of the Presidency, and that the agreement for the use of the port ofPločehad not been ratified.[63]

TheCroatmember of the Presidency,Dragan Čovićcontinuously supported the construction of the Bridge and stated that "problematizing the construction of Pelješac Bridge is not the official position of Bosnia and Herzegovina. The official position of recent years has been in the sense of encouraging Croatia to continue with such an infrastructure project that is of great importance for Bosnia and Herzegovina as well. In this case, it's about one party's (Party of Democratic Action) position and of a couple of individuals in that party. Croatia complied with all the set conditions. "[64]

TheSerbmember of the PresidencyMladen Ivanićstated that he supported construction and that it was necessary to ensure that maritime arrangements allowed ships to freely travel to Neum.[65][66]

President of Republika SrpskaMilorad Dodikstated in August 2017 that Croatia had the right to build the Pelješac Bridge, adding that Bosniak parties were unnecessarily creating problems.[67]

Traffic

[edit]

Traffic flowon the bridge shows significant seasonal fluctuations, withsummermonths reaching highest numbers of crossings.[68]

During August 2022, around 455,000 vehicles crossed the bridge.[68]Two million crossings were reached at 30 June 2023, and three million at 12 September 2023.[69]

Awards

[edit]

References

[edit]
  1. ^Thomas, Mark."City of Dubrovnik celebrates the opening of the new Pelješac Bridge".The Dubrovnik Times.Retrieved26 July2022.
  2. ^"Croatia opens long-awaited bridge bypassing Bosnia".Al Jazeera.Retrieved26 July2022.
  3. ^"Pelješac Bridge joined together".28 July 2021.Retrieved29 July2021.
  4. ^"Pelješki most je spojen - Hrvatska je spojena! (YouTube link to the completion of the Peljesac bridge".YouTube.28 July 2021.Retrieved29 July2021.
  5. ^Petrushevska, Dragana (16 February 2021)."Croatia's Peljesac bridge construction project to be completed in 2022 - PM".SeeNews.Retrieved12 May2021.
  6. ^"Connecting Croatia: 65% of Pelješac Bridge complete".22 March 2021.Retrieved16 May2021.
  7. ^"Pelješac Bridge Opening Confirmed for End of July".www.total-croatia-news.com.27 May 2022.Retrieved31 May2022.
  8. ^"Pelješac Bridge To Be Formally Inaugurated On 26 July".www.total-croatia-news.com.21 July 2022.Retrieved24 July2022.
  9. ^Thomas, Mark."City of Dubrovnik celebrates the opening of the new Pelješac Bridge - The Dubrovnik Times".www.thedubrovniktimes.com.Retrieved26 July2022.
  10. ^"Croatia opens long-awaited bridge bypassing Bosnia".Al Jazeera.Retrieved26 July2022.
  11. ^"VIDEO: Southern Dalmatia road connection is completed as Ston bypass opens".Croatia Week.20 April 2023.Retrieved5 May2023.
  12. ^"Jutarnji list - Pelješki most je otvoren, ali nije sve gotovo: Grci upali u probleme s gradnjom pristupne ceste".www.jutarnji.hr(in Croatian). 27 July 2022.Retrieved23 August2022.
  13. ^"Pelješac Bridge Open, But What About Ston Bypass and Access Roads?".www.total-croatia-news.com.27 July 2022.Retrieved12 December2022.
  14. ^"[4KHDR] Driving in Croatia: D414 & D674 from Ston to the New Pelješac Bridge - Pelješki most".www.youtube.com.12 November 2022.Retrieved12 December2022.
  15. ^"When Will the Ston Bypass Get Opened?".www.total-croatia-news.com.27 November 2022.Retrieved25 March2023.
  16. ^Radić, Jure; Šavor, Zlatko; Hrelja, Gordana; Mujkanović, Nijaz."Most Pelješac".Građevinar(in Croatian).Archivedfrom the original on 14 September 2017.Retrieved22 July2021.
  17. ^Pipenabher, Marjan (24 December 2018)."Projektiranje i analiza mosta Pelješac".Elektronički zbornik radova Građevinskog fakulteta(in Croatian and English).8(16).
  18. ^"Pelješac Bridge (Komarna/Brijesta, 2022)".Structurae.Retrieved2 June2020.
  19. ^"Pelješac Bridge - Pipenbaher Consulting, bridge design, viaduct design, wind analysis, - Pipenbaher Consulting Engineers".pipenbaher-consulting.com.Retrieved2 June2020.
  20. ^"Neum Agreement, May 1996"(PDF).Technical annex on a proposed loan to the Republic of Croatia for an emergency transport and mine clearing project.World Bank.15 October 1996. pp. 45–47.Retrieved27 December2010.
  21. ^abc"Nikad ispričana priča o Pelješkom mostu: Tri puta živio, tri puta umro, tri vlade mučio je gradnjom. Opet je oživio".Jutarnji list(in Croatian). 24 August 2011. Archived fromthe originalon 3 March 2016.Retrieved17 May2012.
  22. ^"BiH, Croatia seek agreement on proposed bridge".Southeast European Times. 11 April 2007.Retrieved14 May2010.
  23. ^"Kalmeta and Ljubic on Croatia's plan to build Peljesac bridge".Croatian Ministry of Sea, Tourism, Transport and Development. Archived fromthe originalon 12 June 2007.
  24. ^abSlobodna Dalmacija(12 June 2007)."Kalmeta: Bridge to Peljesac in 2011".Limun.hr.Retrieved14 May2010.
  25. ^"Bosnia vexed by Croatian bridge".BBC. 25 October 2007.Retrieved14 May2010.
  26. ^"Construction on Pelješac Bridge starts, Brijest".T-portal.hr. 24 October 2007.
  27. ^"Kapitalni državni projekt čekat će izlazak iz recesije - Konzerviranje radova - Pelješki most 'tanak' za 1,6 milijarda kuna".Slobodna Dalmacija(in Croatian). 18 December 2009.
  28. ^"Hajdaš Dončić: Nemamo 4 milijarde kuna za Pelješki most".Dnevnik.hr(in Croatian).Nova TV (Croatia).9 May 2012.Retrieved17 May2012.
  29. ^"Pelješki most otišao u povijest. Hajdaš Dončić: Izvođačima će se platiti za već obavljeni posao, ali ne i naknadu za izgubljenu dobit".Jutarnji list(in Croatian). 17 May 2012. Archived fromthe originalon 3 March 2016.Retrieved17 May2012.
  30. ^"Čačić o odustajanju od Pelješkog mosta: To bi bilo kao da ložite peć novčanicama od 100 eura".Novi list(in Croatian). 20 April 2012. Archived fromthe originalon 21 April 2012.Retrieved17 May2012.
  31. ^"Pelješki most otišao u povijest. Milanović: Taj most nije besmislica, ali njegova izgradnja nije dovoljno ozbiljno isplanirana"[Pelješac Bridge is history. Milanović: That bridge is not a nonsense, but its construction was not sufficiently seriously planned].Večernji list(in Croatian). 17 May 2012. Archived fromthe originalon 3 March 2016.Retrieved4 June2012.
  32. ^"Gradilište Pelješkog mosta pretvara se u trajektnu luku za kamione?".Slobodna Dalmacija(in Croatian). 10 May 2012.Retrieved4 June2012.
  33. ^""Plava obilaznica" Neuma: Umjesto mosta i koridora, Hrvatska gradi dva trajekta? "(in Croatian).Index.hr.4 June 2012.Retrieved4 June2012.
  34. ^Bohutinski, Josip (4 June 2012)."Trajekti će biti skuplji i od pelješkog mosta"[Ferries to cost more than the Pelješac Bridge].Večernji list(in Croatian).Retrieved4 June2012.
  35. ^"Nova trajektna linija kopno - Pelješac"(in Croatian).Croatian Radiotelevision.5 June 2012. Archived fromthe originalon 7 January 2013.Retrieved9 June2012.
  36. ^Piše: M.L. ponedjeljak, 10 September 2012. 20:56 (9 October 2012)."Iz Europske unije stiže novac za Pelješki most: Hrvatskoj za predstudiju odobreno 200.000 eura - Vijesti".Index.hr.Retrieved7 September2015.{{cite web}}:CS1 maint: numeric names: authors list (link)
  37. ^abc"Commission approves EU financing of the Pelješac bridge in Croatia".European Commission.7 June 2017.Retrieved4 August2017.
  38. ^"JASPERS: Joint Assistance to Support Projects in European Regions".ec.europa.eu.Retrieved26 March2018.
  39. ^"Peljesac bridge is best solution to connect the south of Croatia".Croatian Times.11 December 2013. Archived fromthe originalon 13 December 2013.
  40. ^"Croatia: Delayed bridge bypassing Bosnia goes ahead".BBC News.BBC Monitoring. 15 July 2015.Retrieved17 July2015.
  41. ^Matijaca, Danni (14 April 2016)."Construction of Pelješac Bridge Starting Soon With or Without EU Funds".Total Croatia News.
  42. ^Pavlic, Vedran (10 October 2016)."Deadlines for Pelješac Bridge Delayed Once Again".Total Croatia News.
  43. ^abc"Croatia Rejects Bosnian 'Threats' Over Peljesac Bridge".7 August 2017.Retrieved26 March2018.
  44. ^"Plenković:Pelješac Bridge Project Will Continue".Retrieved26 March2018.
  45. ^"FOTO: Tri ponude za Pelješki most, Kinezi najjeftiniji".Retrieved16 January2018.
  46. ^"TKO SU KINEZI KOJI BI TREBALI SAGRADITI PELJEŠKI MOST S moćnim državnim konglomeratom dvije hrvatske tvrtke već su ugovorile suradnju".jutarnji.hr.Retrieved16 January2018.
  47. ^Parrock, Jack (30 July 2019)."Much-delayed €420m bridge to connect Croatia back on track".euronews.Retrieved14 November2019.
  48. ^"PHOTOS: Peljesac Bridge progress update".Croatia Week.Retrieved14 November2019.
  49. ^"PHOTOS: Peljesac Bridge progressing at speed".Retrieved18 March2020.
  50. ^Eduard Šoštarić (13 March 2007)."Natječaj za most Jarun je namješten"[Jarun Bridge tender is rigged].Nacional(in Croatian). Archived fromthe originalon 21 December 2012.Retrieved14 May2010.
  51. ^Institut IGH."The Summary Study on the Pelješac Bridge"(PDF).Croatian Ministry of Nature Preservation.Iz, u SUO, opisanih hidrogeoloških značajki područja istraživanja uočljivo je da se s pristupnih cesta, a i s Mosta kopno - Pelješac ne smije dopustiti direktan upoj voda u okolni teren bez prethodnog pročišćavanja.[permanent dead link]
  52. ^"The Government needs to issue a public tender for the Peljesac Bridge".Nacional.21 November 2005. Archived fromthe originalon 17 July 2012.Retrieved14 May2010.
  53. ^"The Peljesac Bridge would be much better off as a Tunnel".KorčulaInfo.com. 12 December 2006. Archived fromthe originalon 19 April 2010.Retrieved14 May2010.According to article published inSlobodna Dalmacija[...] prof. dr. sc. Jure Radnić, the head of Bridge and Concrete Department of Faculty of Civil Engineering from Split, Croatia [...] told them that much better and cheaper way to solve the problem of connecting Croatian territories, would be a TUNNEL (!)
  54. ^"Gospođo Kosor, zašto gradite sedam puta skuplje?"[Mrs. Kosor, why build seven times more costly?] (in Croatian). limun.hr. 11 September 2009.Retrieved21 October2011.
  55. ^"Umjesto Pelješkog mosta - podvodni tunel?"[Undersea tunnel instead of Pelješac Bridge?] (in Croatian). index.hr. 29 July 2009.Retrieved21 October2011.
  56. ^Mislav Bago/T.V. (16 June 2015)."Animacija: Ovako bi mogla izgledati nova verzija Pelješkog mosta!".Dnevnik.hr.Retrieved7 September2015.
  57. ^"EK objašnjava: Pelješki most nije uvjet za uspostavu Schengena".Večernji list(in Croatian). 23 October 2010.Retrieved17 May2012.
  58. ^"Sarajevski ultimatum: Bosna do Italije".Globus(in Croatian). Archived fromthe originalon 13 September 2012.Retrieved5 November2012.
  59. ^"BiH protiv nižeg Pelješkog mosta"(in Croatian). Archived fromthe originalon 15 October 2012.Retrieved5 November2012.
  60. ^"Akcija bh. parlamentaraca: Hrvatska ne smije graditi Pelješki most".2 August 2017.Retrieved26 March2018.
  61. ^"Bh. parlamentarci spremaju pismo EU: Lažirana saglasnost BiH za gradnju Pelješkog mosta".Novinska agencija Patria.3 August 2017.Retrieved26 March2018.
  62. ^"Bosnia Determined to Stop Pelješac Bridge Construction".Retrieved26 March2018.
  63. ^"Bosnian Leader:" Croatia Cannot Build Pelješac Bridge "".Retrieved26 March2018.
  64. ^"Čović u Temi dana: Problematiziranje gradnje Pelješkog mosta nije službeno stajalište BiH".Archived fromthe originalon 26 March 2019.Retrieved26 March2018.
  65. ^"Mladen Ivanić: Granicu sa Srbijom riješiti po principu" metar za metar "".
  66. ^"Mladen Ivanić: Milorad Dodik izmišlja, sam sebe ubijedi u stvari koje ne stoje".Archived fromthe originalon 27 March 2018.Retrieved26 March2018.
  67. ^"DODIK POKLOPIO IZETBEGOVIĆA 'Hrvatska ima pravo graditi Pelješki most na svome teritoriju. Bošnjačke strane nepotrebno stvaraju probleme'".Retrieved26 March2018.
  68. ^abcd"Pelješac Bridge hits milestone with three million vehicles crossing".croatiaweek.com.Croatia Week. 12 September 2023.
  69. ^Bohutinski, Josip (12 September 2023)."Preko Pelješkog mosta prošlo više od tri milijuna vozila".vecernji.hr(in Croatian). Večernji list.

Further reading

[edit]
[edit]