Jump to content

Yichang–Wanzhou railway

From Wikipedia, the free encyclopedia
(Redirected fromYiwan Railway)
Yichang–Wanzhou railway
Yichang-Wanzhou section of theShanghai–Wuhan–Chengdu passenger railway corridor
CRH logo
The Yichang–Chongqing route, formed by the Yichang–Lichuan section of the Yiwan line and theYuli (Lichuan–Chongqing)line, shown as a thick red line on the map of China's HSR construction plan
Overview
Other name(s)Yiwan railway
Native nameNghi vạn đường sắt
StatusOperational
OwnerCR Wuhan
CR Chengdu
LocaleHubei province
Termini
Stations24
Service
TypeClass I
SystemChina Railway High-speedChina Railway High-speed
Operator(s)CR Wuhan
CR Chengdu
History
OpenedJuly 1, 2012(2012-07-01)
Technical
Line length377 km (234 mi)
Track gauge1,435 mm(4 ft8+12in)standard gauge
Electrification25 kV 50 Hz AC(Overhead line)
Operating speed
  • 160 km/h (99 mph) max. (Yichang–Lichuan)
  • 120 km/h (75 mph) max. (Lichuan–Wanzhou)
Route map

km
0
Yichang East
Yangtze River Bridge
Yichang South
Chexi
(planned)
Changyang
Baozhen tunnel
(11,595 m)
Langping
(planned)
Yesanguan Tunnel
(13,838 m)
Yesanguan
Gaoping
Luoshuidong
(planned)
Jianshi
Baiyangping
Baiguo
(planned)
Enshi
Yunwushan tunnel
(6,682 m)
Qingkou
Maluqing tunnel
(7,879 m)
Lichuan
288
Liangwu
Wangying
(planned)
Qiyueshan
Qiyueshan tunnel
(10,528 m)
Guancangping
(planned)
Luotian
Guyu
(planned)
Yubeishan
Ganziyuan
(planned)
Wuqiao
Wanzhou Railway Bridge
377
Wanzhou

TheYichang–Wanzhou railway,or theYiwan railway(simplified Chinese:Nghi vạn đường sắt;traditional Chinese:Nghi vạn đường sắt;pinyin:Yíwàn Tiělù) connects the cities ofYichang(HubeiProvince) andWanzhou(ChongqingMunicipality) viaLichuan,Hubei. It was completed in 2010 and forms part of theShanghai–Wuhan–Chengdu passenger railway.Out of the line's total 377 km (234 mi) length, 288 km (179 mi) runs on bridges or in tunnels. According to the chief engineer, Zhang Mei, the line was the most difficult ever constructed in China. Operation started on22 December2010.[1]

Connections

[edit]
TheYichang Railway Bridgeover theYangtze Rivernear the eastern terminus of the railway inYichang.
The railway crosses the Yangtze River a second time near its western terminus, Wanzhou. Pictured is theWanzhou Railway Bridge.

At its eastern end, theYichang East railway station,the Yiwan Railway connects with the high-speedWuhan–Yichang railwaytoHankou(Wuhan).

AtLiangwu railway station,the Yichang–Wanzhou railway connects with the high-speedChongqing–Lichuan railway(Yuli), the main route of the Huhanrong corridor, which provides the most direct connection to Chongqing and on toChengdu.From Liangwu, the Yichang–Wanzhou railway heads north to reach Wanzhou. With the Yuli and Hanyi lines both in operation and in use by high-speed, it will become possible to travel by train between Wuhan and Chongqing in around 5 hours, compared to the 22 hours before the opening of the Yiwan Line.[2]However, the opening of high-speed service (as opposed to "regular" trains) on the Yichang–Wanzhou railway was delayed until July 1, 2014.[3]

Until the Yuli line was completed at the end of 2013, all through traffic on the Yiwan Railway had to go along its entire length, to the line's western terminus at Wanzhou, and then over an existing railway branch toDazhou,Sichuan.From Dazhou, trains could continue both southwest toward Chongqing on theXiangyang–Chongqing railwayand west toward Chengdu on theDazhou–Chengdu Railway.[2]

Layout

[edit]

The 377 km (234 mi) long[4]railway crosses the remarkably difficult terrain of southwestern Hubei (YichangCity andEnshi Tujia and Miao Autonomous Prefecture) and the eastern part of theChongqingMunicipality (Wanzhou District). The region has numerous mountains and is sometimes referred to as "the eastern edge" of theYunnan-Guizhou Plateau.[5][6]Until recently, the region had no railways, and hardly any paved roads (beyondChina National Highway 318,which the new railway more or less parallels).[7]The new (G42 Hurong Expressway) was built along the same corridor as well (seeSi Du River Bridgefor an example of engineering that was required).

Out of the entire length of the rail line, 324 km (201 mi) are in Hubei and 53 km (33 mi) in Chongqing Municipality.[4]Owing to the difficult terrain, the project involved a large number of bridges (including two over theYangtze River:theWanzhou Railway Bridgeand theYichang Railway Bridge) and tunnels. Out of the line's total 377 km (234 mi) length, 288 km (179 mi) runs on bridges or in tunnels. This made the line the most difficult and the most expensive (per kilometre) of all China's railways up to that time. At a cost of U.S.$9.01 millionper kilometre, the per-kilometre construction costs were twice as high as those for theQinghai–Tibet Railwaywhich cost U.S.$4.35 millionper kilometre.[8][9]

Construction history

[edit]
Construction of theWanzhou Railway Bridge,at the western end of the Yiwan line

The railway was first proposed bySun Yat-senin 1903, but construction was not started until 2003 due to the difficulties of the project.[10]According to the chief engineer, Zhang Mei, the line was the most difficult ever constructed in China.[10]

As of mid-2009, the embankments, bridges, and tunnels along the Yiwan Railway had been mostly completed, and about half the rails had been laid.[4]On18 August2010, the line's construction was completed.[10]Local media reported that the line would become operational inNovember 2010.[11]

Trial operations started on 19 November,[12]and regular operation started on22 December2010, with passenger trains fromWuhanrunning toLichuan;[13]on10 January2011 a through-passenger service started from Wuhan toChongqingover the entire Yiwan line.[14]

See also

[edit]

References

[edit]
  1. ^"China's Yichang–Wanzhou railway begins trial operation".RetrievedApril 30,2012.
  2. ^abThree Gorges route linked up,Railway Gazette International,31 August2010
  3. ^Đi Thượng Hải, đi Hàng Châu……7 nguyệt có hi vọng ngồi động xe[Go to Shanghai, Go to Hangzhou... Looking toward the start of EMU service on July 1] (in Simplified Chinese). Thành đô thương báo. 2014-05-11.
  4. ^abcPRC: Yichang–Wanzhou railway Project. Environmental Monitoring Report.Asian Development Bank. Project Number: 35339. June 2009
  5. ^Guo Rui (22 December 2010)."Expensive railway set for its maiden journey".China Daily.Retrieved22 December2010.
  6. ^"China's" most difficult to build "railway to open".English.news.cn. 21 December 2010. Archived fromthe originalon February 9, 2011.Retrieved22 December2010.
  7. ^See, e.g., the characterization of theChina National Highway 318andChina National Highway 209as "unstable and unsafe" in:Yichang–Wanzhou railway (SEIA)(Asian Development Bank,June 2003), p.6
  8. ^"Most expensive rail line in China becomes operational".Times of India.22 December 2010.Retrieved26 December2010.
  9. ^Nghi vạn đường sắt thành Trung Quốc thi công nhất gian nan đoạn đường giá trị chế tạo vì thanh thiết gấp hai ][Yiwan Railway will become China's the most difficult railway construction project. Construction costs twice as high as for the Qingzang Railway] (in Simplified Chinese). Sở võng - sở thiên đô thị báo. 2006-06-30.
  10. ^abc"China's most difficult mountain railway linked up".Xinhua. 18 August 2010. Archived fromthe originalon August 22, 2010.Retrieved23 December2010.
  11. ^Vạn châu thị dân có thể cưỡi xe lửa du Tam Hiệp đập lớn(in Simplified Chinese). Tam Hiệp đô thị báo. 2010-04-19.
  12. ^China's Yichang–Wanzhou railway begins trial operation,2010-11-19
  13. ^Yi-Wan Railway Line Opened.Wuhan News. 26-12-2010
  14. ^“Khó nhất tu đường sắt” nghi vạn đường sắt thông xe[ "Most difficult to build railway" opens for service] (in Simplified Chinese).IfengNews.
[edit]